17th Street Causeway Bridge Project
December 99' Project Update
|
|
|
Date of Report:12/99
information provided by FDOT
| IDENTIFICATION |
| Project No.: 227874-1-52-01 |
Highway No.: SR A-1-A |
Construction Project
Manager: Gregory Lady Phone: (954)524-9189 |
| Feature Intersected:
Intracoastal Waterway |
Construction
Engineering Inspection Consultant: Parsons Brinckerhoff
Construction Services |
| Description: 17th
Street Causeway Bridge Replacement Project |
Prime Contractor: Traylor
Brothers Inc. |
Designer: E. C. Driver and
Associates, Inc. |
|
TIME
|
| Start Date: 09/27/97 |
Season Complete: Winter 2001 |
Elapsed Time(ET) in days: 729 |
Current Total Duration (CTD) in days: 1050 |
Percent Elapsed Time (ET/CTD x 100): 69.4% |
|
PROGRESS
|
| Earnings To Date (E): $42,651,987.94 |
Current Total Cost (CTC): $ 65,543,162.72 |
Percent Actual Progress (E /CTC x 100): 65.1% |
|
WORK THAT IS FINISHED OR
UNDERWAY
|
| North bridge segmental erection complete.
Bascule piers and leaves complete; exodermic decks poured CIP
walls complete. Electrical and mechanical work underway to make
bridge operational. Deck grinding, railings, and construction of
roadway approaches also underway. |
|
UP COMING WORK
|
| Complete electrical & mechanical work on
bascule piers. Finish roadway approaches for North bridge and
miscellaneous work on segmental bridge approaches (railings,
lighting, etc.). |
|
|
|