17th Street Causeway Bridge Project

December 99' Project Update

 


Date of Report:12/99

information provided by FDOT

IDENTIFICATION
Project No.: 227874-1-52-01 Highway No.: SR A-1-A Construction Project Manager: Gregory Lady Phone: (954)524-9189
Feature Intersected: Intracoastal Waterway Construction Engineering Inspection Consultant: Parsons Brinckerhoff Construction Services
Description: 17th Street Causeway Bridge Replacement Project Prime Contractor: Traylor Brothers Inc. Designer: E. C. Driver and Associates, Inc.

TIME

Start Date: 09/27/97 Season Complete: Winter 2001 Elapsed Time(ET) in days: 729 Current Total Duration (CTD) in days: 1050 Percent Elapsed Time (ET/CTD x 100): 69.4%

PROGRESS

Earnings To Date (E): $42,651,987.94 Current Total Cost (CTC): $ 65,543,162.72 Percent Actual Progress (E /CTC x 100): 65.1%

WORK THAT IS FINISHED OR UNDERWAY

North bridge segmental erection complete. Bascule piers and leaves complete; exodermic decks poured CIP walls complete. Electrical and mechanical work underway to make bridge operational. Deck grinding, railings, and construction of roadway approaches also underway.

UP COMING WORK

Complete electrical & mechanical work on bascule piers. Finish roadway approaches for North bridge and miscellaneous work on segmental bridge approaches (railings, lighting, etc.).