Evans Crary



Links

New Pile Detail - FDOT

structurae: Evans Crary Sr. Bridge (English Version)

DESIGN — What Happens When Conventional Wisdom is Thrown Out? Great article from Bridge Builder Magazine.

Project Update

Evans Crary - construction photos as of 12-21-99

PROJECT OVERVIEW:

The Evans Crary Bridge consists of two bridges approximately 909 meters long, 15 meters long and navigational channel clearance of 65 ft..  Each bridge will be wide enough to provide two traffic lanes, two emergency lanes, a bicycle lane, and a pedestrian lane.  The original design by Beiswsenger Hoch & Associates was meant to construct the bridge by balanced cantilever method for precast concrete segments, the same method as the recently completed Roosevelt Bridge.  However a redesign was proposed by PCL Inc. and prepared by Finley McNary Engineerings, Inc.  to construct the bridge using span-by-span method.  This redesign has been approved by the Florida DOT for the 55 meter spans.  When the project is completed it will be a record for span-by-span construction in the U.S. The record span lengths at the time of construction was 180 feet. This is the second longest in the world (at time of construction).

 Cost: $30.7 million

Designer:  Beiswsenger Hoch & Associates

Inspection:  Figg Construction Services

Contractor:  PCL Civil Constructors

Owner:  FDOT

FDOT received an AASHTO Award for “Most Innovative Proposal During Construction" for this project.

Original Bids
Contractor Total Bid
PCL Civil Constructors Inc. $30.7
Odebrecht Contractors of Florida $31.7
Misener Marine Construction $32.5
GLF Construction Corporation $34.8
Middlesex Corporation $36.1
Traylor Bros., Inc. $36.3
Recchi America, Inc. $37.9
Granite Construction Co. of Calif. $38.9

 


Information below kindly provided by ASBI



Figure 27: Evans Crary Bridge construction, Florida


Figure 28: Evans Crary Bridge construction, Florida

A balanced cantilever design was revised to a span-by-span segmental design with near-record spans of 180 feet for the Evans Crary Bridge crossing Florida's St. Lucie River by PCL Civil Constructors and Finley McNary Engineers. The redesign resulted in savings of $770,000.00 for the Florida Department of Transportation and facilitated construction in the following ways:

•PCL wanted to access the bridge by water only, and using span-by-span rather than the balanced cantilever method allowed them to do that.
•Because all transportation of the precast segments could be done by water, PCL was able to build larger segmentsă15 feet instead of 10. That meant that one casting machine could be eliminated, saving significant time and money. Transporting by water also reduced the headaches and cost of moving the oversized precast segments by roadway.
•Longer segments provided faster construction and reduced the amount of material, equipment, and labor required.

The bridge's twin, precast segmental structures are 15.044 meters wide, 909 meters long, and are separated by a 450-mm gap. Rising at a vertical grade of 5.2%, the bridge provides a 19.885-meter vertical and 27.440-meter horizontal clearance over the St. Lucie River. It is continuous from end to end with no intermediate expansion joints. The box girder is a constant 2.45 meters deep. The center foundations were

designed for a 9,700 KN ship impact load, using a common footing for both structures where the ship impact load is applied. The piers are cast-in-place with a flared top. Construction views are presented in Figures 27 and 28.

Three main restrictions for the bridge's redesign were:
Box girder section. One of the restrictions for the redesign was that the aesthetics could not be changed. Therefore, the construction team did not revise the exterior dimensions of the cross-section. The original design used varying web thickness and a varying bottom slab thickness. The team selected a constant cross-section for the span-by-span redesign. Then, they reduced the web thickness since draped tendons that would reduce the shear force carried by the webs would be used with the span-by-span construction. Since the cantilever tendons anchoring in the top slab were eliminated, the thickness of the interior haunches was also reduced.

Post-tensioning. The original design was based on straight cantilever tendons and continuity tendons. The redesign used draped external tendons that extended the full span length and were internal to the bottom slab in between deviation points. It also used straight internal tendons in the top and bottom slab that extended the full span length and internal tendons in the bottom slab anchored in blisters. There was over a 50% reduction in the number of tendons and a 40% reduction in the weight of longitudinal prestressing. The team also relocated the temporary PT bars used to compress the epoxy from internal to the top and bottom slabs to external so that they could be reused.

Segments. With the handling of the segments being accomplished entirely with barge-mounted equipment, segment weights up to 95 tons could be used. The original design used split pier segments. The pier segments were redesigned as a single piece that weighed 95 tons. The typical segment length was increased from 3.2 meters to 4.72 meters so that they also weighed 95 tons. Because of the 35% reduction in the number of precast segments (approximately 200 segments eliminated), PCL was able to use only one typical casting machine.

The casting yard is located in Stuart, Florida, about 20 miles from the project site. Segments were barged to the project site. The pier segment machine will be converted to cast the four expansion joint segments after the pier segments are cast. Segments are match-cast using the shortline method of casting and transversely post-tensioned.

On July 14, 1999, at a ceremony in Branson, Missouri, the Florida DOT received AASHTO's award for Most Innovative Proposal During Construction for the Evans Crary Bridge.