The Evans Crary Bridge in Stuart, Florida is well
underway. Below are some photos I took on my recent visit to the project
and the FDOT progress report.
 
Date of Report:12/99
information provided by FDOT
| IDENTIFICATION |
| Project No.: 228821-1-52-01 |
Highway No.: SR A-1-A |
Construction Project
Manager: George Denti, Phone: (561)286-7790 |
| Feature Intersected: Okeechobee
Waterway |
Construction Engineering
Inspection Consultant: Figg Construction Services, Inc. |
| Description: Evans
Crary Sr. Bridge Replacement Project |
Prime Contractor: PCL Civil
Constructors Inc.. |
Designer: Keith and Schnars and
Finley- McNary |
| TIME |
| StartDate: 08/22/98 |
Season Complete: Winter 2001 |
Elapsed Time (ET) in days: 447 |
Current Total Duration (CTD) in days:
1010 |
Percent Elapsed Time (ET/CTD x 100):
44.26% |
| PROGRESS |
| Earnings To Date (E):
$15,984,224.00 |
Current Total Cost (CTC):
$30,806,798.36 |
Percent Actual Progress (E /CTC x 100):
51.89% |
| WORK THAT IS FINISHED OR UNDERWAY |
| All substructure work on the EB bridge is
complete. All WB pile driving that is accessible without existing
bridge demolition is complete. Footers and columns continue to be
cast for those completed pile groups. Span 6EB ,5EB,4EB.and 3EB
are complete. The erection truss is moving to span 2EB. All pier
segments have been cast, and typical segments continue to be cast
daily. |
| UP COMING WORK |
| Pile driving and substructure work for the
westbound bridge to continue, concurrent with erection of
eastbound bridge. Stressing and grouting of spans takes place
concurrent with segment erection. Paving has begun on the western
approach, along with associated drainage and utility work. |
|
|