Fuller Warren Bridge 

        Project Update

 

 

 

 

 

Progress Report Nov. 1999
IDENTIFICATION
Project No.: 72020-3485 / 72020-6526 Highway No.:I- 95 Construction Project Manager: Ken Hill, FDOT
Feature Intersected: St. Johns River Construction Engineering Inspection Consultant: Parsons Brinckerhoff Construction Services
Description: Fuller Warren Bridge Replacement Project Prime Contractor: Balfour Beatty Construction, Inc. Designer: HNTB, Corp.
TIME
Start Date: 6/30/96 Original Season Complete: Spring 2001 Elapsed Time (ET) in days: 1018 Current Total Duration (CTD) in days: 1764 Percent Elapsed Time (ET/CTD x 100): 57.7%
PROGRESS
Earnings To Date (E): $70,060,111.03 Current Total Cost (CTC): $94,695,411.97 Percent Actual Progress (E /CTC x 100): 73.9%
WORK THAT IS FINISHED OR UNDERWAY
Substructure work continues at Bridge 2 and Ramp D.  Posttensioning operations continue on Bridge 3 caps and on the main span beams.  Superstructure crews completed diaphragms at Ramp E and continue diaphragms at Bridge 3.  Roadway crews placed concrete pavement at Ramp E.  Work on the main channel fender system alternates with beam setting.  Precast operation continue at Greencove Springs.
Pending Supplemental Agreements / Change Orders
MSE wall 2 and 3 changes.