| |
Progress Report Nov. 1999
| IDENTIFICATION |
| Project No.: 72020-3485 /
72020-6526 |
Highway No.:I- 95 |
Construction Project
Manager: Ken Hill, FDOT |
| Feature Intersected: St.
Johns River |
Construction Engineering
Inspection Consultant: Parsons Brinckerhoff Construction
Services |
| Description: Fuller
Warren Bridge Replacement Project |
Prime Contractor: Balfour
Beatty Construction, Inc. |
Designer: HNTB, Corp. |
| TIME |
| Start Date: 6/30/96 |
Original Season Complete:
Spring 2001 |
Elapsed Time (ET) in days: 1018 |
Current Total Duration (CTD) in days:
1764 |
Percent Elapsed Time (ET/CTD x 100):
57.7% |
| PROGRESS |
| Earnings To Date (E):
$70,060,111.03 |
Current Total Cost (CTC):
$94,695,411.97 |
Percent Actual Progress (E /CTC x 100):
73.9% |
| WORK THAT IS FINISHED OR UNDERWAY |
| Substructure work continues at Bridge 2 and Ramp
D. Posttensioning operations continue on Bridge 3 caps and
on the main span beams. Superstructure crews completed
diaphragms at Ramp E and continue diaphragms at Bridge 3.
Roadway crews placed concrete pavement at Ramp E. Work on
the main channel fender system alternates with beam setting.
Precast operation continue at Greencove Springs. |
| Pending Supplemental Agreements / Change
Orders |
| MSE wall 2 and 3 changes. |
|
|