PROJECT OVERVIEW The Lynn Cove
Viaduct cut a path through the forested slopes of the BlueRidge
Parkway. Figg and Muller Engineering developed a span-by-span,
gantry-launch assembly of precast box segments, and the building of the
next pier support from the finished span in order to cause minimum
disturbance to the environment. This is known as top down
construction.
When the Lynn Cove Viaduct was finished it was as
if it was placed there by a giant hand from above. To view more about
a gantry
crane system click here.
|
|